Phase 2 infrastructure

Six bridges and the networks for the eastern phase

Under constructionas of Nov 2025 Phase 2

Works under way since Nov 2025 per MEED.

Freyssinet lists a Phase 2 infrastructure contract of SAR 3.2 billion over 30 months, with six bridges. MEED reported that Haif began $480 million (about SAR 1.8 billion) of Phase 2 works in November 2025. The two figures appear to describe the same joint venture at different scopes, which is our hypothesis, not a confirmed split.

Key facts

Total contract (Freyssinet) SAR 3.2 billion
Sources: Freyssinet Saudi Arabia
Total Phase 2 infrastructure contract per Freyssinet · as of Jan 2026
About SAR 1.8 billion ($480m)
Sources: 1 source
MEED, Nov 2025; probably the Haif share of the joint venture, not the total · Nov 2025
Medium confidence

Sources

  1. Industrial Facilities - Freyssinet Saudi Arabia · Freyssinet Saudi Arabia
  2. Contractor begins $480m King Salman Park infrastructure works · MEED, 5 Nov 2025
  3. Our projects - Haif Company · Haif Company

King Salman Park, in your inbox

Choose the briefings you want: park news, investment and housing, the environment, arts, visiting. Independent and sourced, sent only when there is something worth telling you.

Send me

Free. Confirm by email, unsubscribe in one click. We never share your address. All newsletters

Suggest a correction

We welcome corrections from the project team, journalists and readers. Please include a source link if you can.