How far along is King Salman Park?
The park is being delivered in phases. Here is the status of every place by phase, with source dates so you can see how fresh each claim is.
as of 16 Nov 2026
The big picture
Each segment is sized by the number of places in that status.
- Under construction 31
- Planned 14
- Announced 8
- Completed 6
- Being replanned 1
- In design 1
The three phases
A phase sets the order of delivery, not necessarily an opening date.
Phase 1
2- Art ParkUnder constructionas of Sep 2026
- Phase 1 site-wide infrastructureUnder constructionas of Oct 2026
Phase 2
2- Loop and Boulevard bridgesUnder constructionas of Jan 2026
- Phase 2 infrastructureUnder constructionas of Nov 2025
Phase 3
1- Royal Golf CourseBeing replannedas of Sep 2026
What has been said about progress
Progress percentages come from different publishers and measures, so we show each with its source and date.
| Expected opening |
Initial phases late 2026; substantial completion 2027
Sources: MEED +1Sources2
Low confidence
|
|---|---|
| Bridges in Phase 2 |
6 bridges (4 on the Loop, 2 on the Boulevard)
Sources: Freyssinet Saudi ArabiaSources1
Medium confidence
|
| Announced opening year |
2026 (announced July 2024)
Sources: Saudi Press Agency +1Sources2
Medium confidence
|
| Handover to the Ministry of Culture |
Due within 3 to 6 months of 30 Sep 2026
Sources: MEED
Medium confidence
|
| Soil deliveries |
About 1,000 trucks a night
Sources: The B1M
Low confidence
|
| Construction contracts awarded |
About 95% (Phases 1 and 2)
Sources: MEED
About 93% (March 2026)
Sources: 1 sourceSources1
Over 90% (2025)
Sources: 1 sourceSources1
|
Construction milestones
2019 plan: full completion reported as 2040
Arabic press coverage of the 2019 launch gave 2040 for full completion. Later official timelines do not repeat it and now point to 2027 for substantial completion and 2030 for full completion.
Sources: Ajel
Planting season restarts: about 4 million plants this year
Landscaping restarts at 50,000 to 60,000 plants a day. A temporary water plant is producing about 50,000 cubic metres a day, and 95% of Phase 1 and 2 contracts are awarded.
Sources: MEED
Smart operations and maintenance building reported complete
Sabq reported the 35,000 square metre building complete in June 2026. In September it became the Foundation's interim home inside the park.
Sources: MEED +1
Retaining walls complete: 17 km of local stone
The Foundation announced the retaining walls finished: 17 kilometres, built with 122,500 tonnes of local Riyadh stone, shaping the wadis, hills and plateaus.
Sources: Al Madina (SPA)
Sources1
Al Madina (SPA)Press
Phase 2 infrastructure works begin
Haif started roads, power, water, irrigation, sewage, stormwater and district cooling works for the second phase.
Sources: MEED
Haif awarded Phase 2 infrastructure
MEED reported the award in July 2025 at about SAR 1.8bn (USD 480m). Freyssinet lists a larger SAR 3.2bn Phase 2 contract for the joint venture, so the two figures measure different things.
Sources: MEED
Construction images show the Royal Arts Complex rising
ArchDaily published construction photographs of Bofill's complex: 13 structures totalling about 320,000 square metres.
Sources: ArchDaily
Early reporting: completion in 2024-25
Early reporting pointed to completion around 2024-25. That target was not met. Later timelines moved to a phased opening from late 2026 and substantial completion in 2027.
Sources: Oxford Business Group
Royal Arts Complex reported 48% complete
A Foundation executive told MEED that structural works on the complex were done and construction was 48% complete. More than 13 million cubic metres of soil had been excavated.
Sources: MEED
Water and sewage package: Al Bawani and Wetico selected
MEED reported the pair selected for the water treatment complex, a package worth over USD 500m.
Sources: guest.meed.com
Landscaping contracts worth about USD 2.5bn
Nesma & Partners (about USD 2bn) and Al-Rashid (about USD 330m) won the landscaping and earthworks packages, the biggest planting job in the park's story.
Sources: MEED
District cooling plant contract awarded to SNC-Lavalin
SNC-Lavalin received a 27-month EPC contract for the park's first district cooling plant, with an ultimate capacity of 60,000 refrigeration tonnes.
Sources: Trade Arabia
Sources1
Trade ArabiaSecondary
Plan for the first infrastructure package: finish by March 2023
The contractor's profile gives 18 months from September 2021, so March 2023, for the site-wide infrastructure package. Phase 2 infrastructure followed in 2025.
Sources: Freyssinet Saudi Arabia
Sources1
Freyssinet Saudi ArabiaPrimary
Royal Arts Complex construction launched
The Foundation's board, chaired by the Crown Prince, launched construction on the Royal Arts Complex, more than 500,000 square metres with a museum, theatre, library, cinema and institute for traditional arts.
Sources: King Salman Park Foundation
Sources1
King Salman Park FoundationPrimary
Modern Building Leaders selected for the Royal Arts Complex
MEED reported Modern Building Leaders as contractor for the complex, at about SAR 7.5bn (USD 2bn). Later reports quote a lower figure, so the value depends on the source and scope.
Sources: MEED
Visitor Centre construction starts
The Foundation awarded the building contract to a national company and began work on the 90,000 square metre Visitor Centre, designed by David Adjaye with rammed-earth walls.
Sources: King Salman Park Foundation
Sources1
King Salman Park FoundationPrimary
First major contracts: about USD 1bn (SAR 3.85bn)
The Foundation awarded SAR 3.847bn of work for site preparation, tunnels and bridges on Abu Bakr Al-Siddiq and Al Urubah roads, and groundwork for the Royal Arts Complex. This marks the real start of construction.
Sources: King Salman Park Foundation +1
Sources2
King Salman Park FoundationPrimary
Arab NewsPress
Site-wide infrastructure package begins
The Freyssinet and Haif joint venture reports starting the site-wide package in September 2021, covering about 13 square kilometres of roads, drainage, irrigation, power and data.
Sources: Freyssinet Saudi Arabia
Sources1
Freyssinet Saudi ArabiaPrimary
2019 plan: construction to begin in the second half of 2019
At the launch, the Foundation said work on the four projects would start in the second half of 2019. Construction in fact began in the third quarter of 2021.
Sources: King Salman Park Foundation
Sources1
King Salman Park FoundationPrimary
So, is it open?
What we know about opening and visiting, on one page.