Where the work stands

How far along is King Salman Park?

The park is being delivered in phases. Here is the status of every place by phase, with source dates so you can see how fresh each claim is.

as of 16 Nov 2026

Status

The big picture

Each segment is sized by the number of places in that status.

  • Under construction 31
  • Planned 14
  • Announced 8
  • Completed 6
  • Being replanned 1
  • In design 1
Timeline

The three phases

A phase sets the order of delivery, not necessarily an opening date.

Phase 1

2

Phase 2

2

Phase 3

1
Key facts

What has been said about progress

Progress percentages come from different publishers and measures, so we show each with its source and date.

Expected opening Initial phases late 2026; substantial completion 2027
Sources: MEED +1
ArchDaily, Feb 2026; not reconfirmed after the Sept 2026 MEED reports, and no date announced · as of Feb 2026
Low confidence
Bridges in Phase 2 6 bridges (4 on the Loop, 2 on the Boulevard)
Sources: Freyssinet Saudi Arabia
Freyssinet project page · as of Jan 2026
Medium confidence
Announced opening year 2026 (announced July 2024)
Sources: Saudi Press Agency +1
Target from the Saudi Museums Commission; not reconfirmed since and not met as of 12 Nov 2026 · as of Jul 2024
Medium confidence
Handover to the Ministry of Culture Due within 3 to 6 months of 30 Sep 2026
Sources: MEED
MEED window, about Dec 2026 to Mar 2027; handover of operations, not a public opening · as of Sep 2026
Medium confidence
Soil deliveries About 1,000 trucks a night
Sources: The B1M
The project team, interviewed in The B1M's video (sponsored by Parsons, the park's project manager), November 2026. A spoken, rounded figure: night-time deliveries to avoid Riyadh's daytime traffic · as of Nov 2026
Low confidence
Construction contracts awarded About 95% (Phases 1 and 2)
Sources: MEED
Share of Phase 1 and 2 construction contracts awarded, per the acting CEO as reported by MEED on 30 September 2026. Awarded is not built. · as of Sep 2026
About 93% (March 2026)
Sources: 1 source
An earlier reading of the same measure in March 2026 coverage; consistent with progress to 95% by September. A secondary report that we did not read in full. · Mar 2026
Over 90% (2025)
Sources: 1 source
The Foundation's 2025 brochure said over 90% of construction packages were under contract. · Jan 2025
Why figures differ →
Construction

Construction milestones

Timeline →
2040Target

2019 plan: full completion reported as 2040

Arabic press coverage of the 2019 launch gave 2040 for full completion. Later official timelines do not repeat it and now point to 2027 for substantial completion and 2030 for full completion.

Sources: Ajel
30 Sep 2026

Planting season restarts: about 4 million plants this year

Landscaping restarts at 50,000 to 60,000 plants a day. A temporary water plant is producing about 50,000 cubic metres a day, and 95% of Phase 1 and 2 contracts are awarded.

Sources: MEED
10 Jun 2026

Smart operations and maintenance building reported complete

Sabq reported the 35,000 square metre building complete in June 2026. In September it became the Foundation's interim home inside the park.

Sources: MEED +1
14 May 2026

Retaining walls complete: 17 km of local stone

The Foundation announced the retaining walls finished: 17 kilometres, built with 122,500 tonnes of local Riyadh stone, shaping the wadis, hills and plateaus.

Sources: Al Madina (SPA)
5 Nov 2025

Phase 2 infrastructure works begin

Haif started roads, power, water, irrigation, sewage, stormwater and district cooling works for the second phase.

Sources: MEED
Jul 2025

Haif awarded Phase 2 infrastructure

MEED reported the award in July 2025 at about SAR 1.8bn (USD 480m). Freyssinet lists a larger SAR 3.2bn Phase 2 contract for the joint venture, so the two figures measure different things.

Sources: MEED
7 May 2025

Construction images show the Royal Arts Complex rising

ArchDaily published construction photographs of Bofill's complex: 13 structures totalling about 320,000 square metres.

Sources: ArchDaily
2025Target

Early reporting: completion in 2024-25

Early reporting pointed to completion around 2024-25. That target was not met. Later timelines moved to a phased opening from late 2026 and substantial completion in 2027.

Sources: Oxford Business Group

Sources1

  1. Oxford Business GroupSecondary

How we choose sources

13 May 2024

Royal Arts Complex reported 48% complete

A Foundation executive told MEED that structural works on the complex were done and construction was 48% complete. More than 13 million cubic metres of soil had been excavated.

Sources: MEED
5 Mar 2024

Water and sewage package: Al Bawani and Wetico selected

MEED reported the pair selected for the water treatment complex, a package worth over USD 500m.

Sources: guest.meed.com

Sources1

  1. guest.meed.comSecondary

How we choose sources

16 Jun 2023

Landscaping contracts worth about USD 2.5bn

Nesma & Partners (about USD 2bn) and Al-Rashid (about USD 330m) won the landscaping and earthworks packages, the biggest planting job in the park's story.

Sources: MEED
13 Jun 2023

District cooling plant contract awarded to SNC-Lavalin

SNC-Lavalin received a 27-month EPC contract for the park's first district cooling plant, with an ultimate capacity of 60,000 refrigeration tonnes.

Sources: Trade Arabia
Mar 2023Target

Plan for the first infrastructure package: finish by March 2023

The contractor's profile gives 18 months from September 2021, so March 2023, for the site-wide infrastructure package. Phase 2 infrastructure followed in 2025.

Sources: Freyssinet Saudi Arabia

Sources1

  1. Freyssinet Saudi ArabiaPrimary

How we choose sources

25 May 2022

Royal Arts Complex construction launched

The Foundation's board, chaired by the Crown Prince, launched construction on the Royal Arts Complex, more than 500,000 square metres with a museum, theatre, library, cinema and institute for traditional arts.

Sources: King Salman Park Foundation

Sources1

  1. King Salman Park FoundationPrimary

How we choose sources

May 2022

Modern Building Leaders selected for the Royal Arts Complex

MEED reported Modern Building Leaders as contractor for the complex, at about SAR 7.5bn (USD 2bn). Later reports quote a lower figure, so the value depends on the source and scope.

Sources: MEED
23 Jan 2022

Visitor Centre construction starts

The Foundation awarded the building contract to a national company and began work on the 90,000 square metre Visitor Centre, designed by David Adjaye with rammed-earth walls.

Sources: King Salman Park Foundation
22 Sep 2021

First major contracts: about USD 1bn (SAR 3.85bn)

The Foundation awarded SAR 3.847bn of work for site preparation, tunnels and bridges on Abu Bakr Al-Siddiq and Al Urubah roads, and groundwork for the Royal Arts Complex. This marks the real start of construction.

Sources: King Salman Park Foundation +1
Sep 2021

Site-wide infrastructure package begins

The Freyssinet and Haif joint venture reports starting the site-wide package in September 2021, covering about 13 square kilometres of roads, drainage, irrigation, power and data.

Sources: Freyssinet Saudi Arabia

Sources1

  1. Freyssinet Saudi ArabiaPrimary

How we choose sources

Jul 2019Target

2019 plan: construction to begin in the second half of 2019

At the launch, the Foundation said work on the four projects would start in the second half of 2019. Construction in fact began in the third quarter of 2021.

Sources: King Salman Park Foundation

So, is it open?

What we know about opening and visiting, on one page.

Visit →

King Salman Park, in your inbox

Choose the briefings you want: park news, investment and housing, the environment, arts, visiting. Independent and sourced, sent only when there is something worth telling you.

Send me

Free. Confirm by email, unsubscribe in one click. We never share your address. All newsletters

Suggest a correction

We welcome corrections from the project team, journalists and readers. Please include a source link if you can.