Why figures differ

When will the park be finished?

Late 2026, 2027 or 2030?

Explained Updated 12 Nov 2026
The figures, side by side

What each source says

Construction contracts awarded About 95% (Phases 1 and 2)
What it measures
Share of Phase 1 and 2 construction contracts awarded, per the acting CEO as reported by MEED on 30 September 2026. Awarded is not built.
Date
Sep 2026
Source
Sources: MEED
High confidence

Why the figures differ

These dates mark different milestones. ArchDaily's February 2026 update points to initial phases opening in late 2026 and substantial completion in 2027, and Gerber told Arab News in October 2025 that full completion is expected in 2030. Back in 2019 the launch material gave 2040 for full completion, and an early target of 2024 to 2025 has passed. As of 12 November 2026 no asset has opened and no opening date has been announced. MEED reported on 30 September that a phased soft-opening plan was going to the board, and the Royal Arts Complex is due to be handed to the Ministry of Culture between December 2026 and March 2027.

What we show

A dated status: 'preparing a phased soft opening, no date announced (12 November 2026)'. The 2027 and 2030 targets are shown as substantial and full completion, each with its source.

What would resolve it

The Foundation publishing its soft-opening plan and a dated first-opening area.

Sources

Sources: Royal Commission for Riyadh City +4
Figures explained →

More figures explained

King Salman Park, in your inbox

Choose the briefings you want: park news, investment and housing, the environment, arts, visiting. Independent and sourced, sent only when there is something worth telling you.

Send me

Free. Confirm by email, unsubscribe in one click. We never share your address. All newsletters

Suggest a correction

We welcome corrections from the project team, journalists and readers. Please include a source link if you can.