When was Package 4 awarded?

November 2025 or 10 March 2026?

Awaiting confirmation Updated 12 Nov 2026
The figures, side by side

What each source says

Package 1 fund SAR 4 billion (about $1.1bn)
What it measures
Size of the real estate development fund for the first land parcel, announced September 2023. A fund size, not a construction cost.
Date
Sep 2023
High confidence
Package 5 value More than SAR 11 billion (about $3bn)
What it measures
Value of the Kolaghassi-led development as announced at MIPIM, March 2026.
Date
Mar 2026
High confidence

Why the figures differ

Retal's disclosure dates the award to 10 March 2026, the day the Foundation announced the new packages at MIPIM, and Saudi Gulf Projects and Arab News follow that date. A separate press release carried by Zawya, noted in our research file, says the award was completed in November 2025, with agreements still to be signed. An award can be agreed before the legal agreements are finalised, so the two may describe two steps of the same deal.

What we show

We show 10 March 2026 as the announcement date and note November 2025 as an earlier reported award, with both sources.

What would resolve it

A statement from Retal or the Foundation saying when the award was agreed and when the agreements were signed.

Figures explained →

More figures explained

King Salman Park, in your inbox

Choose the briefings you want: park news, investment and housing, the environment, arts, visiting. Independent and sourced, sent only when there is something worth telling you.

Send me

Free. Confirm by email, unsubscribe in one click. We never share your address. All newsletters

Suggest a correction

We welcome corrections from the project team, journalists and readers. Please include a source link if you can.