Contractors

Modern Building Leaders (MBL)

Main contractor for the Royal Arts Complex.

Saudi Arabia

Modern Building Leaders was selected in 2022 to build the Royal Arts Complex. MEED reported the contract at SR7.5bn (about $2bn) in June 2023; a 2026 report gives about $1.76bn, so we show the contract value as reported rather than as settled. The complex was reported 48% complete in 2024 and is due to be handed to the Ministry of Culture around December 2026 to March 2027.

What it works on

Main contractor; contract reported by MEED at about SAR 7.5bn (about $2bn)

Royal Arts Complex

SAR 7.5bn contract value

Sources: MEED

Timeline

May 2022Construction

Modern Building Leaders selected for the Royal Arts Complex

MEED reported Modern Building Leaders as contractor for the complex, at about SAR 7.5bn (USD 2bn). Later reports quote a lower figure, so the value depends on the source and scope.

13 May 2024Construction

Royal Arts Complex reported 48% complete

A Foundation executive told MEED that structural works on the complex were done and construction was 48% complete. More than 13 million cubic metres of soil had been excavated.

King Salman Park, in your inbox

Choose the briefings you want: park news, investment and housing, the environment, arts, visiting. Independent and sourced, sent only when there is something worth telling you.

Send me

Free. Confirm by email, unsubscribe in one click. We never share your address. All newsletters

Suggest a correction

We welcome corrections from the project team, journalists and readers. Please include a source link if you can.